I Street - 102nd Street to EB I-80 On-Ramp (OPW 53897) (COMPLETED)

About the Project

The existing pavement surface on I Street from 102nd Street to the eastbound I-80 on-ramp has deteriorated over the years and has reached the end of its serviceable life. This project will reconstruct
the roadway to a new concrete pavement section with curb and gutter, construction of an enclosed underground storm sewer system, and construction of a sidewalk and ADA curb ramps on the south side of the new roadway. West of the 108th Street intersection, the driving lane and turn lane configuration will be replaced in a similar manner as it currently exists. East of 108th Street intersection to the railroad tracks, the addition of a center turn lane is planned.
 
At this time, it is anticipated the construction activity will occur in two separate segments, the portion west of the 108th Street intersection and the portion east of the 108th Street intersection. Each of these segments will occur in a separate timeframe. While construction occurs west of the 108th Street intersection, I Street will be closed from 108th Street to the eastbound I-80 on-ramp. When construction occurs east of the 108th Street intersection, eastbound traffic is anticipated to be maintained for local access only to those properties located between 102nd Street and 108th Street.
 

click on image to enlarge

This project is being undertaken as a part of the Street Preservation Fund Program. For more information on these projects, click here.

Project Schedule

 

Construction Updates

September 12, 2023
I street is now open to traffic.  The remaining minor work is to be completed under lane closures if needed.
 
June 6, 2023
Starting next Monday, June 12, crews will begin work on Phases 3A and 3B located at the railroad tracks west of 102nd Street. All properties located on I Street west of the railroad tracks will need to access properties from 108th Street; and all properties located east of the railroad tracks will need to access their properties from 102nd Street.
 
May 24, 2023
I Street eastbound between 102nd Street and 108th Street will be closed to "local access only" for concrete pouring of the westbound lane. Crews are scheduled to pave the westbound section of I Street east of 108th Street beginning May 26th at 9 a.m. This work will require large equipment that will take up the eastbound lane and may cause long delays in the area for access to properties located between 108th and 102nd Street. For the safety of our crews and all those traveling on I Street during this work, please expect delays during the paving operation and be cognizant of crews in the area. Flaggers will be at the intersections of 108th and 102nd Street to allow vehicles access to the affected businesses. 
 
May 17, 2023
The current phases of work along I Street – Phases 2B/2C – will be substantially complete this Friday, May 12, 2023. Work will begin on Phases 2D/2E next Monday, May 15, 2023. Please see attached notice for information. During this work, one-way eastbound I Street traffic east of 108th Street will be moved to the south side of I Street on the newly poured pavement. Business access is as follows:
  • Full access to businesses on the south side of I Street will be provided during this phase of work
  • Access to businesses on the north side will be maintained at all times via temporary surfacing or at secondary driveways to properties.
For more information: 
 
March 30, 2023
Crews are scheduled to pave a section of I Street east of 108th Street 4/6. This work will require large equipment that will take up additional lane width and may cause 5-10 minute delays in the area for access to properties located between 108th and 102nd Streets. For the safety of our crews and all those traveling on I Street during this work, please expect delays during this paving operation and be cognizant of crews in the area. The pavement work is tentatively scheduled for Thursday, 4/6 or Friday, 4/7, dependent on weather, and we will keep you updated as the schedule progresses. See below for map of paving area.
Map.png
 
February 27, 2023
A press release was sent to stakeholders regarding resuming work. View the press release here: 
November 22, 2022
Construction on the I Street project will temporarily shut down for the winter months by the end of the day Saturday, November 26, 2022. With the winter shut down, I Street from 108th to 102nd streets will reopen to all traffic at that time. Utility relocation and storm sewer work along the project corridor over the winter months is anticipated within the city’s right-of-way.
For more information: 
 
September 19, 2022
The first phase of work on the City of Omaha’s I Street project between 108th Street and the Interstate 80 (I-80) ramp is nearing completion, and crews are tentatively scheduled to reopen traffic in late September. The project has progressed ahead of schedule, and therefore construction of Phase 2 is also scheduled to begin in late September. The contractor, Charles Vrana & Son Construction Company, will being construction of Phase 2 on Monday, September 26, 2022. Please see the construction phasing details and maps below for reference.
Crews will begin with Phase 2A on I Street from 108th to 102nd streets. During this construction, a full closure of I Street will be in place from 108th east for approximately 700 feet.
 
For more information:
 
August 15, 2022
Vrana continues to make progress along the corridor, moving into the next phase of work starting Monday, August 22, 2022. Please see attached for details on turning restrictions at 108th and I streets as part of this work.
 
For more information: 
 
July 7, 2022
Starting next Wednesday, July 13, 2022 work will begin on the west half of the 108th Street intersection. North and southbound traffic will be maintained on 108th Street under two-way head-to-head traffic and temporary traffic control shifting southbound traffic to the east half of the intersection.
 
For more information: 
 
June 16, 2022
Starting tomorrow (Friday, June 17, 2022), roadway work on the south side of I Street from the I-80 ramp will progress to 110th Street and roadway removals will begin at the 110th and I Street intersection. Click here for more information.
 
May 2022
The City of Omaha’s “I” Street project between 108th Street and the Interstate 80 (I-80) ramp, is scheduled to begin on Tuesday, May 10, 2022. Utility relocation work has begun and will continue throughout the project corridor for the remainder of the 2022 construction season into 2023. Utility agencies will coordinate with properties as needed during their operations. The contractor, Charles Vrana & Son Construction Company, plans to begin construction with a full closure of “I” Street from 108th Street to the I-80 ramp beginning May 10, 2022.
 
For more information:
 
 

 Contact Us

  • To submit a comment or receive project updates, join the project mailing list through our Contact Form.
  • To provide your input about a specific location within the project area, visit the City Map.

 Queries

Stephen Edloff
Project Manager, Public Works Division 
City of Omaha
402-444-5220