Storm clean up efforts are ongoing throughout the city. Please refer to the map of the current clean up efforts  to determine if your neighborhood has been completed.

If you notice any down traffic signs because of the July 31st storm, please report them to the Mayor's Hotline at 402.444.5555 or online at Omaha Hotline

Project Update | August 28, 2024

Beginning Thursday, September 5, only right turns will be allowed entering and exiting Patterson Drive from 168th Street.  The restriction will be in place for 3 weeks to allow the contractor to complete paving in the median areas of 168th Street.

168th Street West Center Road to Q St

The existing two-lane roadway is at capacity and often experiences delays during the peak hours. Improving safety for all transportation users, enhancing traffic operations, decreasing peak hour congestion, and improving drainage control are the primary benefits of the project.

Project Features

Improvements

  • increase from two to four lanes with center median
  • new roadway with curb and gutter
  • enclosed storm sewer
  • sidewalks
  • retaining walls
  • noise walls
  • bridge over Zorinsky Lake
  • traffic signals

Schedule

  • Preliminary Design Work: 2007-2017
    • Noise, Traffic, Geotechnical, and Environmental Analyses 
    • Preliminary Design
  • Final Design Activities: 2018-2022
    • Additional Field Exploration
    • Final Design
    • Right-of-Way Acquisition
    • Letting and Bidding
  • Construction: 2023-2024
    • Utility Relocation
    • Construction Preparation
    • Construction Begins
Map showing the project area on 168th Street from W Center Road to Q Street

Contact the Project Team

Project Contacts

Troy Staroscik
Project Manager, Public Works 
City of Omaha
402-444-5220
Troy.Staroscik@cityofomaha.org