Project Update | December 19, 2024
Beginning in mid-January 2025, southbound 72nd Street will be closed at I-80, creating a full closure of 72nd Street from I-80 to F Street. Northbound 72nd Street will also remain closed for approximately six months. View the detour.
72nd & D Street Bridges
The existing bridge is reaching the end of its useful life and the corridor is over capacity during peak travel times. The key benefits of this project is to improve capacity and safety, and decrease congestion.
Project Features
Improvements
- Replace existing bridges with a wider, lower maintenance bridge or bridges
- Three lanes of traffic in each direction
- Sidewalk on east side of road
Schedule
- 2017 - 2023: Preliminary Design Work
- Noise, Traffic, Geotechnical, and Environmental Analyses
- Preliminary Engineering Work
- 2023: Final Design, Right-of-Way Acquisition, and Letting & Bidding
- 2024-2025: Utility Relocation, Construction Begins
- Late 2025: Construction Substantially Complete
Document Library
Reports & Studies
Contact the Project Team
Project Contacts
Everett Owen
Project Manager, Public Works
City of Omaha
402-444-5220
Everett.Owen@cityofomaha.org