North 24th St Streetscape Improvements
The purpose of this project is to enhance the safety, accessibility, and aesthetics of North 24th Street from Ohio Street to Sahler Street.
Project Features
Improvements
- Pedestrian nodes to shorten crossing distances
- On street parallel parking
- Sidewalks and ADA curb ramps
- Landscaping
- Signage
- Pedestrian-scale lighting
- Possible traffic calming
- Possible sewer modifications
Schedule
- Design Notice to Proceed: February 2025
- Preliminary Design Submittal: May 2025
- Right-of-Way (if necessary): June 2025 – April 2026
- Final Design Submittal: May 2026
- Bid for Construction: August 2026
- Construction Begins: Spring 2027
Status Updates
May 2, 2025
General Project Management
-
BID to provide street lighting pole evaluation and feedback on May 30, 2025
Design (PE) Status
- Schemmer to revise the City’s comments of the 10% Plans and Cost Estimates
- Schemmer submitted the Urban Design Review Board application on May 23, 2025
- Schemmer is currently performing roadway drainage analysis
Environmental (NEPA) Status
- Historic structure report submitted to NDOT and City for review
- Threatened and Endangered species review in progress
Upcoming Milestones
- City to provide 10% Plans and Cost Estimates to BID after Schemmer revision of City’s Comments
- Plan-in-Hand (PIH) submittal due May 28, 2025 (revised from May 12th)
- Post PIH Plan submittal due August 8, 2025 (revised from July 23rd)
- Public Information Meeting (after PIH) TBD
Document Library
Reports & Studies
Community Engagement
February 2025 North 24th St BID Stakeholder Meeting
January 2024 North 24th St BID Stakeholder Meeting
- Presentation
- Original Concept
Contact the Project Team
Project Contacts
Dean Dunn, P.E.
Project Manager, City of Omaha
402-444-5220
Dean.Dunn@cityofomaha.org