CN 22924 Midtown Medical Bikeway
The Midtown Medical Center Bikeway Connection project will enhance the connectivity of the larger regional bike and pedestrian network by creating a safe connection separated from vehicle traffic. It will pass through the University of Nebraska Medical Center (UNMC) campus - an activity center with some of the highest rates of walking and biking in Omaha. This will help connect high-needs areas and key destinations across Omaha’s regional bike and pedestrian network.
Project Features
Improvements
- Creates a safer, fully separated bikeway
- Strengthens the regional bike and pedestrian network
- Provides a direct route through the high-activity UNMC campus
- Improves access for high-needs neighborhoods
- Connects key destinations across Omaha
- Supports more walking and biking citywide
Schedule
- Preliminary Design and Environmental: Fall 2025 – Fall 2026
- Environmental: Fall 2025 - Winter 2027
- Final Design: Winter 2026 – Winter 2027
- Right of Way Process: Spring 2028 – Winter 2028
- Utility Relocations: Spring 2028 – Winter 2028
- Construction: Winter 2028 - Spring 2030
Document Library
Design Plans, Studies & Reports
Community Engagement
Contact the Project Team
- To submit a comment or receive project updates, join the project mailing list through our contact form.
- To provide your input about a specific location within the project area, visit the City Map.
Project Contacts
Kristi Evans, P.E.
Project Manager, Public Works
City of Omaha
402-444-5220
Kristine.Evans@cityofomaha.org